The city launched its current planning effort in February 2013. The planning effort included the preparation and adoption of the following:
- Final Environmental Impact Report
- Master Infrastructure Plan
Master Infrastructure Plan Map
- Town Center and Waterfront Plan
Town Center and Waterfront Plan Boundary
- New Zoning Map
Zoning District Map
These documents were completed and approved in February of 2014. Subsequently, the city approved the Alameda Point Waterfront and Town Center Specific Plan for the area around the Seaplane Lagoon.
The city is selling some property parcel by parcel and others in blocks. The project for 800 housing units at Site A (part of the Waterfront Town Center) is partially completed.