Memo Regarding Street Sections associated with the City's Adaptive Reuse Infrastructure Project within Alameda Point, January 23, 2019

Excerpt:

Exhibits:
1. Recent Developments and Planned Projects at Alameda Point
2. Proposed Adaptive Reuse Infrastructure Project Street Sections

...

EXECUTIVE SUMMARY

The first three phases of the Adaptive Reuse Infrastructure Project include backbone streets which are bordered by Monarch Street to the west, Pan Am Way to the east, West Tower Avenue to the South, and West Redline Avenue and West Midway Avenue to the north. The Transportation Commission is requested to approve the proposed street sections in these areas so that the Public Works Department can complete its design plans for this work. Construction scheduled to begin in 2020.